Lund-Ross Constructors  

COMPLETED PROJECTS
George Beadle Middle School

 
 

George Beadle Middle School

Overview

Location

Millard, Nebraska

Cost

$2.7 Million

Owner

Millard Public Schools

Architect

Zenon Beringer Mabrey Partners

Photo Gallery


Details

Lund-Ross oversaw the construction of the new 126,000 square-foot George Beadle Middle School in southwest Omaha. The school features classrooms equipped with televisions, DVD players and computers, as well as a library, gymnasium, cafeteria, computer labs, science labs and common areas for students. An environmentally friendly ground loop system that was created by drilling 385 wells throughout the jobsite; the unique system provides the school with year-round heating and cooling. Extreme winter conditions during construction required a strict spring and summer schedule to finish in time for the 2001-2002 school year. The project was completed on time and within budget.

Return to Projects Page